...
Exit Criteria | Status/Notes | ||
---|---|---|---|
Test automation and CI is 100% complete with “required for version” | Done. (PR#13718 & PR#14080) | ||
No defects with high/critical exposure or “required for version” | Done. (PR#13718 & PR#14080) | ||
No new daily or weekly regression test failures (failures not already on master branch) | Done. (PR#13718 & PR#14080) | ||
All tests are passing for feature in weekly and daily regression tests | Done. (PR#13718 & PR#14080) | ||
Performance and scale testing executed according to test plan/required requirements. Results are reviewed and approved | Done. (Dalton) | ||
SDL Code scans are competed (Coverity, Bandit, Checkmarx, Snyk). For all scans, all issues have been dispositioned, and the issues that are required per SDL rules have been fixed. |
| ||
SAFE review executed if required | SAFE review is not needed. | ||
Any new dependencies identified and Oked by ESAD OSPDT owner | No new dependencies added. | ||
Does not regress endurance testing from current master baseline with feature enabled |
| AR:
| |
Does not regress scale testing from current master baseline with feature enabled |
| AR:
| Kano
|
Manual test plans and “out-of-box experience” testing are 100% executed with “required for version”. Manual test results are recorded | N/A, all new test cases are automated. | ||
Feature branch is up to date with master |
|
Feature Completion Criteria
...
Exit Criteria | Status/Notes |
---|---|
Requirements are defined in SRS Jira Project. | Done. |
Design document is complete, reviewed, and approved utilizing the team template. | Done. |
Test plan for feature is complete, reviewed, and approved utilizing the team template. Security validate plan is also updated if applicable. | Test plan had been discussed with the team. All tests had been automated. (Makito) |
Planned software feature is 100% implemented with “required for version”. | Done. |
All user documentation updated and reviewed (e.g., admin guide, user guide). | |
Code coverage results have been reviewed to identify gaps in testing, and test plan has been updated and executed accordingly. Functional and branch coverage each are equivalent or better than master. | |
Usability is evaluated and results are reviewed. |
...